WHITE GATE WATER TREATMENT PLANT
Uisce Éireann, working in partnership with Cork County Council, has commenced works to improve the Whitegate Regional Public Water Supply with a major upgrade of Kilva Water Treatment Plant. This investment will ensure a safe, secure, and reliable supply of drinking water to approximately 10,300 people in the region.
Glanua has been appointed Contractor.
​
The Works included:
-
Provision of a new 6,000,000 litre/day water treatment plant, on a site adjacent to the existing plant and reservoir.
-
Construction of a new 450,000 litre raw water balancing tank.
-
A new coagulation, flocculation and clarification system.
-
A new filtration system with rapid gravity filters.
-
Ultraviolet (UV) Disinfection - including two new UV reactors.
-
Construction of a new clear water tank.
-
All associate buildings, control and ancillary items.
-
Decommissioning of the existing water treatment plant.
​
This project will address risks to water quality by providing enhanced treatment facilities at a brand-new water treatment plant adjacent to the existing plant.
​
MEICA Consulting Engineers Ltd provided MEICA Resident Engineering Services including review of Contractor's Design for the project. MEICA Consulting Engineers were working for Nicholas O' Dwyer on this project.